|
July 7, 2010
Community Wide Survey
If you happen to be one of those randomly selected for our
Community Wide Survey, please take a few minutes to complete the survey and send
it back to Leisure Vision in the accompanying postage paid envelope.
Leisure Vision will be making a formal presentation to the
park district upon completion of the process highlighting the results of the
survey. This presentation is tentatively scheduled for August. The
results of this survey will serve as an integral planning tool over the next 3-5
years as the park district considers the allocation of its resources.
Thank you for your continued support!
July 6, 2010
Woodglenn Park Update: Construction Schedule
This is the tentative construction schedule for the Woodglenn
Park Development Project. While every effort will be made to complete this
project on time, conditions such as weather, union strikes, materials
availability, and others may delay the project from time to time. Periodic
updates will be provided on our web site in the event this schedule is impacted
by any of the above or other conditions beyond our control.
Anyone with specific questions about the project is encouraged to contact
superintendent of parks Aaron Cerutti.
| July |
August |
September |
October |
Nov |
| 05 |
12 |
19 |
26 |
02 |
09 |
16 |
23 |
30 |
06 |
13 |
20 |
27 |
04 |
11 |
18 |
25 |
01 |
| |
|
Mobilization & Installation of Silt Fence |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Mass Earthwork |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Re-Spread Top Soil (Phase 1) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping (Phase 1 areas) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Underground Utilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Re-Spread Top Soil (Athletic Fields) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Spread and Disc Biosolids |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Irrigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Install Backstop |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fine Grade & Seed Athletic Fields |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Parking Lot, Walks and Paths |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pavilion Foundation & Underground Utilities |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pavilion Construction |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping/Native Turf |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Install Signange |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Punch List |
|
|
|
|
|
|
|
|
|
July 6, 2010
Woodglenn Park Update:

Anyone with specific questions about the project is encouraged to contact
superintendent of parks
Aaron Cerutti.
June 21, 2010
Woodglenn Park Update:
At their meeting on June 16, the Lisle Park District Board of
Park Commissioners awarded the contract for the Woodglenn Park Development
project. The contract was awarded to Benchmark Construction, a general
contractor out of Bartlett, Illinois, in an amount not to exceed $905,897.17;
$194,000 under budget. Construction is scheduled to begin during the week of
July 5th, however you may see some staging begin during the week of June 28th.
The project schedule still calls for substantial completion in October.
Anyone with specific questions about the project is encouraged to contact
superintendent of parks
Aaron Cerutti.
May 25, 2010
LEGAL NOTICE: INVITATION TO BID LISLE PARK DISTRICT
Notice is hereby given to Contractors that the Lisle Park District will be
receiving sealed bids for the Woodglenn Park Development Project.
Specifications and drawings will be available from the Lisle Park District, 1825
Short Street, Lisle, IL 60532 between the hours of 8:30 a.m. and 5:00 p.m.
Monday through Friday. There is a $50.00 non-refundable deposit for each
set of plans.
Each bid must be placed in a sealed envelope marked “Lisle Park District,
Woodglenn Park Development Project. Bid Package #_____, DO NOT OPEN”, and
addressed to the Lisle Park District, 1825 Short Street, Lisle, Illinois 60532.
Attention: Aaron Cerutti. Bids will be opened at 10:00 a.m. on Tuesday,
June 15; bids received after that time will be rejected.
A mandatory pre-bid meeting will be held on Tuesday, June 1, 2010 at 11:00 a.m.
at the Lisle Park District administrative offices, 1825 Short Street, Lisle,
Illinois.
The Board of Park Commissioners, Lisle Park District, Lisle, Illinois, reserves
the right to waive all technicalities, to accept or reject any or all bids, to
accept only portions of a proposal and reject the remainder. Bids shall
not include federal excise tax or state sales tax. An Exemption
Certificate will be furnished by the park district at the request of the bidder.
All bids will remain firm for 60 days after the bid opening.
All contracts for work herein must adhere to all elements of the Prevailing Wage
Act (820 ILCS 130/1-12).
Minority business firms are encouraged to submit bids, and successful contract
bidders are encouraged to utilize minority businesses as subcontractors for
supplies, equipment, services, and construction.

|